1.
|
Construction of gutter from Dinaraj Govekar house to Kanoji house and from their to Gansham Hotel in ward no.2 at Sada, Vasco-da-gama. |
Rs.5,61,535.50 |
Completed |
2. |
Construction of footpath from Agnel house to Tommy bar in ward no.3, Vasco-da-gama. |
Rs.2,51,954.31 |
Completed |
3.
|
Demolishing old dilapidated Municipal toilet block of four seaters and construct new toilet block near Appa Bagli house in Ward No.3 at Sada, Vasco-da-Gama. |
Rs.1,84,091.08 |
Completed |
4.
|
Supply of 100 RCC slabs in Ward No.4 at Sada, Mormugao, Vasco-da-Gama. |
Rs.97,200.00 |
Completed |
5.
|
Construction of gutter from Parab’s house to existing road in Ward No.4 at Sada, Mormugao, Vasco-da-Gama. |
Rs.2,76,481.25 |
Completed |
6.
|
Construction of footpath near Shantaram Morjekar house in Ward No.5, Vasco-da-Gama. |
Rs.1,16,603.13 |
Completed |
7.
|
Construction of retaining wall near Manerkar house at Rumdawada in Ward No.5, Vasco-da-Gama. |
Rs.1,24,374.60 |
Completed |
8.
|
Construction of footpath near Gama’s house at Bogda in Ward No.5, Vasco-da-Gama. |
Rs.1,16,603.13 |
Completed |
9.
|
Construction of footpath from El-monte Theatre to Suki’s house in Ward No.5, Vasco-da-Gama. |
Rs.1,16,603.13 |
Completed |
10.
|
Construction of retaining wall near Chandrakant Kambli house in Ward No.5 at Rumdawada, Jetty, Vasco-da-Gama. |
Rs.1,22,755.58 |
Completed |
11.
|
Construction of gutter and steps from Devekar house to Subhash Tambolkar house, Gulab Naik house to Mahadev Kumtekar house, Agnel Fernandes house to Mahadev Navelkar house in ward no.6 at Bogda, Mormugao, Vasco-da-gama. |
Rs.2,15,920.14 |
Completed |
12.
|
Construction of gutter near Vikram Parsekar house and Gurudas Mayekar house in ward no.6 at Bogda, Vasco-da-gama. |
Rs.3,47,584.20 |
Completed |
13.
|
Construction of retaining wall near Mr. Gopinath Morje house, Ward no.6, Bogda, Near Salgaokar Temple, Vasco-da-gama. |
Rs.1,47,500.52 |
Completed |
14.
|
Construction of gutter near M.K. Sayyed house to Gonsalves house in ward no.7 at Baina, Vasco-da-gama.
|
Rs.1,51,317.50 |
Completed |
15.
|
Construction of footpath in and around Shafi Masjid, Ward No.7, Baina, Vasco-da-Gama. |
Rs.1,67,580.00 |
Completed |
16.
|
Construction of gutter from Police Outpost, Baina to the road near Ali Scrap Yard, Vasco-da-Gama. |
Rs.3,25,691.00 |
Completed |
17.
|
Construction of drainage from Basweshwar Temple to Main Road, Ward No.7, Baina, Vasco-da-Gama. |
Rs.2,64,554.50 |
Comlpeted |
18.
|
Construction of footpath with chequerred tiles from back of Shaikh house to Raymond house in Ward No.8, Vasco-da-Gama. |
Rs.1,35,675.38 |
Completed |
19.
|
Construction of gutter either side of the road from Donabatt Building to Bara Chawl with slabs, Ward No.8, Vasco-da-Gama. |
Rs.3,60,414.00 |
Completed |
20. |
Repair and improvement of existing road with full grout from Argentina house to Hollycross chapel near last bus stop sasmollem Baina, ward no.9, Vasco-da-gama. |
Rs.1,75,115.45 |
Completed |
21. |
Development of Cross (Church) near Machado Building at Church Road, Baina in Ward No.9, Vasco-da-Gama. |
Rs.72,618.00 |
Not yet started due to complaint |
22. |
Repair for gutter near Anjuman High School, Islampura, Baina in Ward No.9, Vasco-da-Gama. |
Rs.63,828.37 |
Completed |
23. |
Construction of footpath from Mangesh house to Main Road in Ward No.9, Mangoor Hill, Vasco-da-Gama. |
Rs.1,54,440.00 |
Completed |
24. |
Repair and Improvement of gutter with fixing pre-cast R.C.C. slabs near Hassan Garage, Baina, Ward No.9, Vasco-da-Gama. |
Rs.1,50,744.50 |
Completed |
25. |
Repair and Improvement of existing passage/footpath leading from Ajij Khan house to Ivott Pinto, Bhute Bhat, Baina, Ward No.10, Vasco-da-Gama. |
Rs.1,25,805.00 |
Completed |
26. |
Construction of gutter with slabs and footpath in front of Sunflower building in ward no.11, Vasco-da-gama.. |
Rs.3,60,710.20 |
Completed |
27. |
Construction of gutter with R.C.C. slabs in front of kamat Nursing Home in ward no.11, Vasco-da-gama. |
Rs
.3,06,919.80 |
Completed |
28. |
Construction of gutter with R.C.C. slabs from Sabina Dias house to Graciana D’Souza house near Kapre Temple behind Tilak Maidan in Ward No.12, Vasco-da-Gama. |
Rs.1,61,558.32 |
Completed |
29. |
Construction of gutter/footpath near Hanumanth Temple, Saibini Bhat in ward no.13, Vasco-da-gama. |
Rs.3,35,258.13 |
Completed |
30. |
Construction of gutter behind Lobo house at Vollant in Ward No.13, Vasco-da-Gama. |
Rs.1,04,148.50 |
N.O.C. from landlord
Not executed
|
31. |
Construction of footpath from Kamaxi Bar to the Bakal house at Mundvel in Ward No.13, Vasco-da-Gama. |
Rs.1,49,997.52 |
Completed |
32. |
Construction of footpath from Suresh Chari house to Gurudas Chari house at Mestawada in Ward No.XIV, Vasco-da-Gama. |
Rs.20,523.60 |
Completed |
33. |
Construction of footpath from Main Road of Mangor to Dilip Satardekar house link to Temple at Orulem in Ward No.14, Vasco-da-Gama. |
Rs.67,776.33 |
Completed |
34. |
Reconstruction of gutter near Pundalik Parab at Belabai in Ward No.14, Vasco-da-Gama. |
Rs.1,30,505.35 |
Completed |
35. |
Construction of gutter infront of Manesh Arolkar at Belabai in Ward No.14, Vasco-da-Gama. |
Rs.1,25,718.07 |
Completed |
36. |
Supplying and Fixing of R.C.C. slab in Ward No.14, Vasco-da-Gama. |
Rs.1,38,800.00 |
Completed |
37. |
Construction of footpath and Repairs of gutter near Hanuman Temple at Gandhinagar in Ward No.15, Vasco-da-Gama. |
Rs.2,74,206.86 |
Completed |
38. |
Construction of gutter and Improvement of existing access between Olijoan Henriques Apartments and Solan Valley View for a length of 80 m in Ward No.16, Vasco-da-Gama. |
Rs.4,26,376.45 |
Completed |
39. |
Providing, Supplying and Fixing R.C.C. slabs on various existing open gutters in Ward No.16 in Phase (I), Vasco-da-Gama. |
Rs.1,69,000.00 |
Completed |
40. |
Providing, Supplying and Fixing R.C.C. slabs at various places in Ward No.17, Mormugao Municipal Council, Vasco-da-Gama. |
Rs.1,69,000.00 |
Completed |
41. |
Construction of footpath opposite Almeida house, surrounding nearby houses and upto Raghuvir Sakhalkar house in Ward No.17, Mormugao Municipal Council, Vasco-da-Gama. |
Rs.2,07,007.50 |
Completed |
42. |
Construction of footpath from main road to Joseph Rodrigues house near Ganapati Temple, New Vaddem, Ward No.17, Vasco-da-Gama.. |
Rs.57,010.95 |
Completed |
43. |
Construction of footpath/pathway/access from Dharma Gadekar house to Shankar Kharnekar house and laying R.C.C. slabs on open gutter near house of Shankar Kharnekar house in Ward No.18, New Vaddem of Mormugao Municipal Council, Vasco-da-Gama. |
Rs.75,151.56 |
Completed |
44. |
Construction/Repair to footpath from Gaurish Naik house to Hannumant Devsekar house in Ward No.18, New Vaddem of Mormugao Municipal Council, Vasco-da-Gama. |
Rs.79,083.51 |
Completed |
45. |
Repair and Reconstruction to the existing gutter from house of Sheila L. Naik to Leeladhar Kumbharjuvekar house and further in Ward No.18, New Vaddem of Mormugao Municipal Council, Vasco-da-Gama. |
Rs.79,564.45 |
Completed |
46. |
Providing, Supplying and Fixing R.C.C. slabs on various existing open gutters in Ward No.18 in Phase (I), Vasco-da-Gama. |
Rs.1,69,000.00 |
Completed
|
47. |
Repair to the existing footpath/pathway/access from Rama Naik house to Meghraj Gawle house in Ward No.18, New Vaddem, Vasco-da-Gama. |
Rs.39,463.12 |
Completed |
48. |
Construction of gutter from Raja Bandodkar house to Sudan Chodankar house in Ward No.18, New Vaddem, Vasco-da-Gama. |
Rs.92,198.57 |
Completed |
49. |
Construction of footpath from David house to Ellawwa M. Harijan and Sulochana house to Chandrappa Harijan house and Mahadev Salgaokar house to Renuka’s house in Ward No.19 in Housing Board Colonies, Vasco-da-Gama. |
Rs.3,01,127.50 |
Work in progress |
50. |
Providing, Supplying and Fixing R.C.C. slabs on various existing open gutters in Ward No.19 in Phase (I), Vasco-da-Gama. |
Rs.1,69,000.00 |
Completed |
51. |
Construction of footpath from Vithal Temple to Ramchandra Patekar house in Ward No.18/19 of Mormugao Municipal Council at Shantinagar, Vasco-da-Gama. |
Rs.1,21,635.93 |
Completed |
52. |
Construction of footpath from New Vaddem Main Road to Manohar Rane’s house, Main Road to Luis Mascarenhas house, Main Road to Rajan Bhagat house & Main Road to Sneha Fondekar house & some road side surrounding area in Ward No.19 of Mormugao Municipal Council, Vasco-da-Gama. |
Rs.1,01,100.00 |
Completed |
53. |
Construction of footpath from Dodamani house to Chandrappa Harijan house and Chandrappa Harijan house to Emnappa Harijan house in Ward No.19 in Housing Board Colonies, Vasco-da-Gama.. |
Rs.3,73,398.10 |
Completed |
54. |
Construction of footpath near Ashok house at Adarshnagar in Ward No.20, Vasco-da-Gama. |
Rs.1,24,218.44 |
Completed |
55. |
Construction of steps from upstream side near Satyappa house at Chaferon, Adarshnagar in Ward No.20, Vasco-da-Gama. |
Rs.1,29,057.80 |
Completed |
56. |
Construction of steps from Electricity Transformer near Shobha/Kamat house at Chaferon, Adarshnagar in Ward No.20, Vasco-da-Gama. |
Rs.1,29,057.80 |
Completed |
57. |
Construction of gutter from Santosh Nerker house to main Nallah, Ward No. 20, Merces Vaddem, Vasco-da-Gama. |
Rs.2,64,940.80 |
Completed |
58. |
Construction of road from Singh’s house to Girish house at Merces, Vaddem, Vasco-da-Gama. |
Rs.94,991.40 |
Completed |
59. |
Supply and fixing of RCC slabs in City area of Mormugao Municipal Council Jurisdiction. |
Rs.1,39,256.00 |
Completed |
60. |
Beautification and Fencing outside Hindu Crematorium at Khariwada, Vasco-da-Gama. |
Rs.3,98,346.02 |
Completed |
61. |
Construction of road from Lakhani house to Adhia house in Ward No.6 at Desterro, Bogda, Vasco-da-Gama. |
Rs.1,50,991.60 |
Completed |
62. |
Construction of footpath with chequered tiles and small open gutter from Katem Cross road to Pradeep house in Ward No.VIII |
Rs.73,924.00 |
Completed |
63. |
Construction of passage from Bhau Tendulkar’s residence to Vaingankar Stores and Reshma Beauty Parlour to Vinayak Sawant house in Ward No.19, Vasco-da-Gama. |
Rs.95,073.90 |
Completed |
64. |
Repair and Improvement of the existing staircase by constructing retaining wall leading from Desterro Chappel to Borkar house (Repairing Stretch near house of Gansham Nivathkai and Francis Pereira) in Ward No.6, Vasco-da-Gama. |
Rs.2,51,090.88 |
Completed |
65. |
Construction of gutter with R.C.C. slabs and footpath from Colaco Arcade Building to Francis Gonsalves house in Ward No.6, Vasco-da-Gama. |
Rs.64,602.32 |
Completed |
66. |
Construction of gutter with R.C.C slab and footpath from Sadanand Banji house to Jamini Kanolkar house in Ward No.02, at Sada, Vasco-da-Gama. |
Rs.2,20,742.00 |
Completed |
67. |
Construction of gutter with RCC slab from Sahara Bar to Yeshwant Shetye house and Santosh Honawarkar house to Babu Talvankar house in Ward No.02, Sada, Vasco-da-Gama. |
Rs.2,71,254.00 |
Work in progress |
68. |
Construction of gutter from Sunil Morje house to Kolamkar house at Sada, Vasco-da-Gama. |
Rs.91,673.00 |
Work in progress |
69. |
Maintenance and Repairs to the existing gutter near Jeevan Bar to the house of Laxman Madkaikar and surrounding area in Ward No.03 at Sada, Mormugao. |
Rs.1,25,350.00 |
Work completed |
70. |
Construction of footpath from Suresh house via Lata house to Suraj house in Ward No.04, Sada, Vasco-da-Gama. |
Rs.2,28,585.00 |
Work in progress |
71. |
Construction of footpath behind MDLB Hospital in Ward No.06, Vasco-da-Gama. |
Rs.1,95,930.00 |
Work in progress |
72. |
Reconstruction of gutter with RCC slab from Dr. A. Fernandes to Dr. A. P. Borkar in Ward No.07, Baina, Vasco-da-Gama. |
Rs.4,93,917.00 |
Work in progress |
73. |
Development of footpath from Mr. Gaspar Rodrigues house to Mr. Victor Rosario in Ward No.08, Baina, Vasco-da-Gama. |
Rs.1,88,428.00 |
Tendered |
74. |
Construction of footpath at various places along the sea shore at Holy Cross, Yakab house, Maboob and Hussain house in Ward No.08, Baina, Vasco-da-Gama. |
Rs.86,975.00 |
Completed |
75. |
Reconstruction of gutter from Haldankar house to Parsekar house in Ward No.09, Baina, Vasco-da-Gama. |
Rs.2,01,677.00 |
Completed |
76. |
Construction/repairs to footpath near Mahadev Rathod house, Bandagi Sab Hulgi house, Hirrapa Kumbhar, Rajesh Mulla, Chandrappa & some nearby houses near Maruti Temple & surrounding area in Ward No.10 of Mormugao Municipal Council, Vasco-da-Gama in (Phase I). |
Rs.3,81,393.00 |
Work order issued |
77. |
Construction of gutter from backside of Old Power House to Mariam Electrical Shop. |
Rs.1,65,836.00 |
Work order issued |
78. |
Providing, Supplying and Fixing factory made precast RCC slabs at various places on open gutter etc. in Ward No.10, Vasco-da-Gama |
Rs.2,37,000.00 |
Work order issued |
79. |
Construction of gutter with RCC slabs in front of Canara Bank in Ward No.11, Vasco-da-Gama. |
Rs.1,33,402.00 |
Completed |
80. |
Improvement of footpath in front of Bakery Opposite Syndicate Bank, Vasco City, Ward No.11, Vasco-da-Gama. |
Rs.61,974.00 |
Work not started |
81. |
Construction of gutter covering with RCC slabs from Merciana’s house to St. Andrew Sports Club at P. C. Dongri in Ward No.12, Vasco-da-Gama. |
Rs.1,94,747.00 |
Work under process |
82. |
Providing pipe railing at Vollant in front of Peter Antao, Anand Kudalkar, Dicholkar house, Rodrigues house and near Gomantak Gate Vasco-da-Gama. |
Rs.1,71,191.00 |
Work under process |
83. |
Construction of gutter from Tulsidas Naik along Satardekar house upto the existing gutter, Vasco-da-Gama. |
Rs.1,73,864.00 |
Not started |
84. |
Construction of gutter from Jaidev Naik house along the existing well upto the existing gutter, Vasco-da-Gama. |
Rs.1,06,805.00 |
Not started |
85. |
Repair of existing road from Eknath Naik house to Yashoda Nivas and Repair of cross gutter at Gandhinagar Sawarkarnagar in Ward No.15 of Mormugao Municipal Council |
Rs.2,15,726.00 |
Completed |
86. |
Repair of existing road from Mangor Sports Club to Oswin Bar and Construction of new road from Oswin Bar to Edwin Pereira to Lopes house at Mangor Hill in Ward No.15 of Mormugao Municipal Council |
Rs.3,60,144.00 |
Work order not issued |
87. |
Construction of footpath starting from road to old footpath near Shree Krishna Temple at Dactolem in Ward No.16 of Mormugao Municipal Council, Vasco-da-Gama |
Rs.1,71,054.00 |
Work started |
88. |
Beautification of in and around area of Rastroli Temple at New Vaddem in Ward No.17 of Mormugao Municipal Council |
Rs.1,96,837.00 |
Work started |
89. |
Construction of footpath/passage with G. I. railing from Nabi Shab house to Vijay house along Railway track at New Vaddem in Ward No.18, Mormugao Municipal Council. |
Rs.2,78,079.00 |
Work order issued
Work not started
|
90. |
Construction of road from Gopi Manjrekar houseto Kamli house at Chaferan in Ward No.20 of Mormugao Municipal Council. |
Rs.1,73,057.00 |
Work order issued |
90. |
Construction of road from Gopi Manjrekar houseto Kamli house at Chaferan in Ward No.20 of Mormugao Municipal Council. |
Rs.1,73,057.00 |
Work order issued |
91. |
Construction of footpath from Das house to Betgiri house at Merces Vaddem in Ward No.20, Vasco-da-Gama. |
Rs.81,729.00 |
Work order issued |
92. |
Reconstruction of gutter from Parab house to Britto house at Headland Sada. |
Rs.45,676.50
|
Work tendered |
93. |
Supply/Fixing R.C.C. slab to Cover the open gutter Mr. Parab house at Headland Sada. |
Rs.43,740.00
|
Work tendered |
94. |
Proposed reconstruction of gutter with R.C.C slab near Babajan house in Ward No. 02 Headland Sada. |
Rs.46,648.75 |
Work tendered |
95. |
Proposed reconstruction of gutter near Pandre house in ward no.02 at Sada. |
Rs.47,537.50 |
Work tendered |
96. |
Proposed reconstruction of gutter near Vijay Mesta house in Ward No. 03 at Sada, Vasco. |
Rs.47,537.50
|
Work tendered |
97. |
Proposed reconstruction of gutter near Kammuddin Shaikh house in Ward No. 03 at Sada, Vasco. |
Rs.47,537.50
|
Work tendered |
98. |
Proposed reconstruction of footpath near Redkar house in Ward No. 04 at Sada |
Rs.46,237.50
|
Work tendered |
99. |
Proposed reconstruction of gutter near Swapes house in Ward No. 04 at Sada. |
Rs.47,537.50
|
Work tendered |
100. |
Repair of gutter behind Electricity Quarters Nr. Mandakini Morajkar house Ward No. 05 |
Rs.47,537.50
|
Work tendered |
101.
|
Retaining wall near Govt. School Bogda from Shri. Subhash Gawas house to Shri. Bhomdo Shridkar house in Ward No. 05 |
Rs.47,413.20 |
Work tendered |
102. |
Repair of gutter in front of Shri. Manohar Ladu Pednekar house in Ward No.06 |
Rs.47,537.50 |
Work tendered |
103.
|
Repair of footpath from Morje house up to Maria Caetano house in Ward No. 06 |
Rs.46,237.50 |
Work tendered |
104.
|
Construction / Repair of footpath from Fatima Bi Shaikh house to Basir Shaikh house Ward No. 07 |
Rs. 33,654.47 |
Work tendered |
105.
|
Construction of footpath from Cosmos Bar to Original old existing footpath, Ward No.07, Mormugao Municipal Council, Vasco-da-Gama |
Rs.37,912.50 |
Work tendered |
106.
|
Providing, Supplying and Fixing of precast RCC slabs at various places on open gutter in Ward No.07 of Mormugao Municipal Council |
Rs.23,700.00 |
Work tendered |
107.
|
Construction of footpath from Shaikh Majid’s house to Shaikh Yusuf house in Ward No.08 of M.M.C Vasco. |
Rs.36,512.68 |
Work tendered |
108.
|
Construction of footpath / pathway from Sabana house to Existing Road in Ward No. 08 pf M.M.C Vasco |
Rs.37,771.50 |
Work tendered |
109.
|
Construction of footpath near / in front of Manohar’s shop at Baina in Ward No. 08 of MMC. |
Rs.23,769.21 |
Work tendered |
110.
|
Maintenance & Repair & Fixing of Chequerred tiles to the existing footpath & steps near / side of Taiba Masjid in Ward No. 9 of MMC, Vasco. |
Rs. 104,285.18 |
Work tendered |
111.
|
Maintance & Repair to the existing pathway from Rahmat Halkeri house to Yasin Shaikh House near Ganapati Temple Maktum Sab house to Zuleka Bi Shaikh house near Emlikazad area in Ward No. 10 of M.M.C Vasco |
Rs.94,104.61 |
Work tendered |
112.
|
Reconstruction of gutter opposite Gitanjali Building, City Area in Ward No.11, Vasco-da-Gama |
Rs.45,719.02 |
Work order not issued |
113.
|
Supplying and Fixing of R.C.C slab over gutter opposite Gitanjali Building city area in Ward No.11, Vasco |
Rs.47,320.00 |
Work order not issued |
114.
|
Reconstruction of gutter from Thereza house to the shop near the road in Ward No.12, Vasco-da-Gama. |
Rs.42,554.52 |
Work order not issued |
115.
|
Reconstruction of gutter from Joaquim D’Souza house to Bhaarija Shop in Ward No. 12, Vasco-da-Gama. |
Rs.49,598.25 |
Work order not issued |
116.
|
Construction of footpath from Mr. Nabi house to Mr. Borkar house at Pixem Dongri in Ward No.12, Vasco-da-Gama. |
Rs.16,369.00 |
Completed |
117.
|
Construction of footpath from Smt. Carmelina house to Smt. Esperanca house at P. C. Dongri, Ward No.12, Vasco-da-Gama. |
Rs.24,369.00 |
Work under process |
118.
|
Construction of footpath from Mr. Moosa house to Rajaram house at Pixem Dongri in Ward No.12, Vasco-da-Gama.. |
Rs.16,783.00 |
Work under process |
119.
|
Providing & Laying Chequerred Tiles in front of the Cross-at Vollant in Ward No. 13, Vasco-da-Gama. |
Rs.86,209.57 |
Work order not issued |
120. |
Construction of gutter from Anil Navelkar house to the field at Orulem in Ward No. 14, Vasco da Gama. |
Rs.
95,553.40 |
Work order not issued |
121. |
Construction of footpath in front of Basu house at Gandhinagar and covering the near gutter with R.C.C slab in Ward No.15 |
Rs.
45,795.80 |
Work order not issued |
122. |
Construction of gutter at Ranjit Pal house at Gandhinagar Mangor in Ward No.15 Vasco. |
Rs.47,498.60 |
Work order not issued |
123. |
Construction of gutter from Subhash Borkar’s house to Nallah in Ward No. 16 of M.M.C Vasco. |
Rs.
92,493.00 |
Work order not issued |
124. |
Construction of footpath from Akash Pednekar house to main road Hari Shetgaonkar house to main road and near Alex Desouza house Ward No. 17 of M.M.C Vasco |
Rs.
47,608.41 |
Work started |
125. |
Construction of footpath from Maria Pereira house to main road Novso Chodankar house to main road, Janan Antonio Rodrigues house to main road, Natalia Rodrigues house to main road, Babush Nulgaunkar house to main road and near Xaverina Fernandes house in Ward No. 17 of M.M.C Vasco. |
Rs.47,362.25 |
Work started |
126. |
Construction of footpath near Alwin Sarkar house to Sameer house at New Vaddem in Ward No.17 of Mormugao Municipal Council, Vasco-da-Gama |
Rs.14,454.00 |
Completed |
127. |
Construction of footpath near Sainath Naik house to Laximan Fondekar house at New Vaddem in Ward No.17 of Mormugao Municipal Council, Vasco-da-Gama |
Rs
.45,771.00 |
Completed |
128. |
Construction of footpath near Gabriel Fernandes house to Mukund Lotlikar house at New Vaddem in Ward No.17 of Mormugao Municipal Council, Vasco-da-Gama |
Rs.37,942.00 |
Completed |
129. |
Construction of footpath near Pednekar house to Bandekar house near Ganapati Temple at New Vaddem in Ward No.17 of Mormugao Municipal Council, Vasco-da-Gama |
Rs.37,942.00 |
Completed |
130. |
Construction of footpath near John Dias house upto road at New Vaddem in Ward No.17 of Mormugao Municipal Council, Vasco-da-Gama |
Rs.22,886.00 |
Completed
|
131. |
Construction of footpath near Laximan Fondekar house to Mukund Lotlikar house at New Vaddem in Ward No.17 of Mormugao Municipal Council, Vasco-da-Gama |
Rs.30,595.00 |
Completed |
132. |
Construction of footpath near Vishwas Naik house to Sainath Naik house at New Vaddem in Ward No.17 of Mormugao Municipal Council, Vasco-da-Gama |
Rs.17,161.00
|
Completed |
133. |
Construction of footpath at Ulhas Parkar house upto road near Simple Bar, New Vaddem in Ward No.17 of Mormugao Municipal Council, Vasco-da-Gama |
Rs.30,113.00
|
Completed |
134. |
Construction of footpath form Rego Bar to Parashant Raikar house in Ward No. 18 of M.M.C, Vasco |
Rs.67,464.09
|
Work tendered |
135. |
Supplying and Fixing of R.C.C slabs on existing gutter near Liladhar Kumbharjurekar house in Ward No. 18 New Vaddem of M.M.C Vasco |
Rs.20,360.00
|
Work tendered |
136. |
Repair of existing footpath behind People for Animal site and surrounding area at Shantinagar in Ward No.19 |
Rs.45,939.49
|
Work tendered |
137. |
Construction of footpath between Maruti Arolkar house to Mr. Chari house near Santoshi Mata Temple at New Vaddem in Ward No. 19 of M.M.C Vasco. |
Rs.49,690.08
|
Work tendered |
138. |
Construction of footpath from Barbosa house to Sukanti house and surrounding area at Adarshnagar in Ward No. 20 of M.M.C Vasco. |
Rs.94,960.65
|
Work tendered |
139. |
Supplying and fixing of warning sign (No Garbage Zone) at Vaddem Lake in Ward No.20, Mormugao Municipal Council, Vasco-da-Gama. |
Rs.13,710.00
|
Work tendered |
140. |
Surface cleaning of the Nallah from Muslim Kabrastan to Shipyard and to River at Vasco-da-Gama |
Rs.3,12,119.32
|
Work tendered |
141. |
Surface cleaning of the Nallah from Bellabai Chapel to St. Sebastian Chapel and behind the ground at Bhute Bhat, Vasco-da-Gama |
Rs.3,06,704.87
|
Work tendered |
142. |
Surface cleaning of the Nallah from Amelin Gonsalves house to MPT Workshop in the length of 510.00 mts at Vasco-da-Gama |
Rs.94,250.52
|
Work tendered |
143. |
Surface cleaning of Nallah from St. Bellabai Chapel to Tanya Hotel and behind Tanya Hotel at Vasco-da-Gama |
Rs.2,06,425.28
|
Work tendered |
144. |
Cleaning of domestic drinking well of diameter varying between 2.50 mts to 5 mts and having depth from top of parapet to the bottom of well between 5 mts to 15 mts by removing all deleterious material hanging vegetation and silt in Municipal Area, Vasco-da-Gama |
Rs.2,70,000.00
|
Work tendered |
145. |
Supplying and filling of mud at Garbage Treatment Plant, Sada – Phase I |
Rs42,413.00
|
Work tendered |
146. |
Supplying and filling of mud at Garbage Treatment Plant, Sada – Phase II |
Rs.42,413.00
|
Work tendered
|
147. |
Supplying and filling of mud at Garbage Treatment Plant, Sada – Phase III |
Rs.42,413.00
|
Work tendered |
148. |
Upgradation of the existing Animal Shelter at Shantinagar in Ward No.18, Mormugao Municipal Council, Vasco-da-Gama. |
Rs.1,52,440.28
|
Work tendered |
|